8-10 Network Infrastructure Manager User Guide
Change Control
3 Select the Rollback button
This will open a confirmation window.
4 Select Continue to confirm
5 Select Continue to acknowledge the rollback start message
A broadcast message window announces that a rollback is in progress.
6 View the Operation Status panel for rollback progress
While the rollback configuration version loaded, you can view the progress of the
process in the Operation Status panel. The mouse cursor for NIM will remain an
hourglass until the process is complete. You cannot perform any other functions with
Network Infrastructure Manager until the rollback is completed. When the message,
Configuration rollback request was completed successfully., appears in the panel,
the process is complete and you can continue using NIM.
7 Select Update Now, or Update later and Synchronize
Details at the step Choose Update Now, or choose Update Later and later use the
Synchronize icon to update on page 5-3.
8 Select Continue to acknowledge the rollback complete message
A broadcast message window announces that the rollback is complete.